EnerPHit retrofit in one of the prime three-storey period mews dwellings on Adams Row for Grosvenor Estate as part of Estates plan for Carbon Emissions reductions.The Victorian property was built as stable/coach house in 1720 and converted to dwelling between 1886-1892. The aim was to maintain all its existing historical features whilst delivering an efficient building to the highest standards.
Images Graphs Figures Description Strategies Building

Adams Row : Project images

Click on image to preview full size

Adams_Row_2014__Sturgis_Carbon_Profiling.jpg
Adams_Row_2014__Sturgis_Carbon_Profiling_2.jpg
CO2 emissionsPrimary energy requirement
Energy target
EnerPHit

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use - - -
Natural gas use- - -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement - - -
Annual CO₂ emissions - - -
Annual space heat demand - - -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
--
Annual CO₂ emissions
offset by renewable generation
--

Calculation and targets

Whole house energy calculation method
Other whole house calculation method-
Energy target EnerPHit
Other energy targets-
Forecast heating load -

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test--

Project description

StageOccupied
Start date12 April 2014
Occupation date
Location London London  England
Build typeRefurbishment
Building sectorPrivate Residential
Property typeMid Terrace
Construction typeSolid Brick
Other construction type
Party wall construction
Floor area 111.5
Floor area calculation method Treated Floor Area (PHPP)
Building certification  Passivhaus certified building Passivhaus certified building

Project Team

Organisation
Project lead person
Landlord or ClientGrosvenor
ArchitectCarbon Sturgis Profiling
Mechanical & electrical consultant
Energy consultantCarbon Sturgis Profiling
Structural engineer
Quantity surveyor
Consultant
Contractor

Design strategies

Planned occupancy
Space heating strategy
Water heating strategy
Fuel strategy
Renewable energy strategy
Passive Solar strategy
Space cooling strategy
Daylighting strategy
Ventilation strategy
Airtightness strategy
Strategy for minimising thermal bridges
Modelling strategy
Insulation strategy
Other relevant retrofit strategies
Contextual information

Building services

Occupancy
Space heating
Hot water
Ventilation
Controls
Cooking
Lighting
Appliances
Renewable energy generation system
Strategy for minimising thermal bridges

Building construction

Storeys
Volume -
Thermal fabric area -
Roof description
Roof U-value -
Walls description
Walls U-value -
Party walls description
Party walls U-value -
Floor description
Floor U-value -
Glazed doors description
Glazed doors U-value - -
Opaque doors description
Opaque doors U-value - -
Windows description
Windows U-value - -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -